McQueen AnalyticsDecision intelligence + market research

data-center developer and operator

Crusoe, Inc.

Develops Microsoft Abilene and Google Armstrong campuses; sold its pre-development Wyoming site to Google.

Dated commitments & changes

transaction update

Crusoe reports Google's acquisition of its Wyoming site

Crusoe said Google acquired the southeast Wyoming site, ending Crusoe's pre-development role; Tallgrass helped develop its power strategy.

Southeast Wyomingsite acquisition reported complete
Sources and context

No price, IT capacity or commercial-operation date established by this release. Governmental approvals are a developer assertion; the individual approvals were not audited.

construction update

Crusoe identifies Google's Armstrong County campus under construction

Crusoe confirmed its developer role and reported construction continuing after a June 2025 groundbreaking.

Armstrong County near Claude, Texasunder construction
Sources and context

September is the disclosure date, not the construction start. Adjacent wind-farm MW are generation capacity and are not assigned as campus IT load.

project announcement

Crusoe and Lancium announce Childress campus

Crusoe will design, build and operate the data center; Lancium owns the land and manages energy infrastructure. The customer was unnamed.

1 GWGrid-connected campus capacityfull-scale grid-connected capacityChildress campusplannedCrusoe / Lancium ↗
Childress, Texasplanned
Sources and context

Construction was expected in Q3; a subsequent start is not established by this release.

construction update

Crusoe announces adjacent Microsoft campus with site preparation underway

Crusoe reported land clearing for two Microsoft buildings adjacent to its existing Abilene campus; first energization was targeted for mid-2027.

900 MWOn-site power plantgeneration designnew Microsoft campusplannedCrusoe ↗
336 MWCritical IT load per buildingIT load designeach of two new buildingsdesignedCrusoe ↗
Abilene, Texassite preparation
Sources and context

Separate from the original Oracle/OpenAI campus. Two 336 MW IT buildings total 672 MW design load; the 900 MW headline refers to the power/site plan. Existing-campus completion by end-2026 remains a forecast at this announcement.

operational update

Oracle reports two Abilene buildings operating

Oracle said two buildings were fully operational, the remaining campus was on track and leasing for its additional 4.5 GW OpenAI commitment was complete.

Abilene, Texaspartially operational company report
Sources and context

Oracle published the post at 10:40 PM Eastern on March 8, which was March 9 in UTC. The 4.5 GW figure describes leasing across multiple sites, rather than Abilene's operating capacity. Oracle's statement does not negate Katti's account of redirecting an incremental expansion.

scope change

OpenAI redirects additional Abilene capacity to other locations

Sachin Katti said OpenAI considered a further Abilene expansion and chose other locations while its existing campus and wider buildout continued.

Abilene, Texasexpansion redirected
Sources and context

No exact size, lease termination date or financing cause is established by this post.