No price, IT capacity or commercial-operation date established by this release. Governmental approvals are a developer assertion; the individual approvals were not audited.
Crusoe announces adjacent Microsoft campus with site preparation underway
Crusoe reported land clearing for two Microsoft buildings adjacent to its existing Abilene campus; first energization was targeted for mid-2027.
900 MWOn-site power plantgeneration designnew Microsoft campusplannedCrusoe ↗
336 MWCritical IT load per buildingIT load designeach of two new buildingsdesignedCrusoe ↗
Abilene, Texassite preparation
Sources and context
Separate from the original Oracle/OpenAI campus. Two 336 MW IT buildings total 672 MW design load; the 900 MW headline refers to the power/site plan. Existing-campus completion by end-2026 remains a forecast at this announcement.
Oracle said two buildings were fully operational, the remaining campus was on track and leasing for its additional 4.5 GW OpenAI commitment was complete.
Abilene, Texaspartially operational company report
Sources and context
Oracle published the post at 10:40 PM Eastern on March 8, which was March 9 in UTC. The 4.5 GW figure describes leasing across multiple sites, rather than Abilene's operating capacity. Oracle's statement does not negate Katti's account of redirecting an incremental expansion.