≈$14BDevelopment cost commitmentcommitted development costBuildings and long-lived power, cooling and connectivity infrastructureapproximatelyMeta ↗
El Paso, Texasventure announced
Sources and context
Closing was expected after the announcement and has not been verified. BlackRock-managed funds would own 80%; Meta would own 20%. Opening was targeted for 2028. Debt, equity, distributions and guarantees overlap with the development costs; they cannot be added as separate project spending.
>$50BExpansion investmentannounced investmentRichland Parish expansion described by Metagreater thanMeta ↗
Richland Parish, Louisianaexpansion announced
Sources and context
The page also displays July 12; this record uses the leading announcement date. Capacity describes the planned buildout, rather than commissioned output. The expansion amount may overlap prior campus financing. The included costs have not been reconciled.
Meta announced construction of an AI data center in Tulsa and described its expected local investment and operating jobs.
>$1BRegional investmentannounced investmentTulsa facility at completiongreater thanMeta ↗
≈100 jobsOperating jobsforecast permanent jobsTulsa facility once operationalapproximatelyMeta ↗
Tulsa, Oklahomagroundbreaking announced
Sources and context
Announcement date uses the first displayed page date; the page also shows April 20. Physical ceremony timing and subsequent completion were not independently verified.