McQueen AnalyticsDecision intelligence + market research

cloud provider and campus operator

Microsoft Corporation

Microsoft reports its own Mount Pleasant construction and operations. Its first facility is distinct from later campus phases.

Dated commitments & changes

construction update

Microsoft extends Mount Pleasant soil-hauling schedule

Microsoft said soil hauling would continue through year-end with less material moved each day to reduce construction impacts.

Mount Pleasant, Wisconsinsite work continuing
Sources and context

The rolling update supplies a month only. Earthworks for later development do not change the reported operational status of the first facility.

operational update

Microsoft reports Fairwater fully operational

Microsoft announced completion of its first Mount Pleasant facility after equipment startup began in April. The adjacent second facility remained under construction.

Nearly 550 peopleOnsite full-time employeescompany reported employmentFirst Mount Pleasant facilitynearlyMicrosoft ↗
Mount Pleasant, Wisconsinoperational company reported
Sources and context

June 23 is the public confirmation date; startup occurred in April. No IT megawatts are disclosed. This does not mean the entire multi-phase campus is complete.

construction update

Crusoe announces adjacent Microsoft campus with site preparation underway

Crusoe reported land clearing for two Microsoft buildings adjacent to its existing Abilene campus; first energization was targeted for mid-2027.

900 MWOn-site power plantgeneration designnew Microsoft campusplannedCrusoe ↗
336 MWCritical IT load per buildingIT load designeach of two new buildingsdesignedCrusoe ↗
Abilene, Texassite preparation
Sources and context

Separate from the original Oracle/OpenAI campus. Two 336 MW IT buildings total 672 MW design load; the 900 MW headline refers to the power/site plan. Existing-campus completion by end-2026 remains a forecast at this announcement.

local agreement

Van Meter authorizes Microsoft development agreement

Council unanimously authorized Resolution 2026-25 for a development agreement with Microsoft.

5 for · 0 against

Approve Resolution 2026-25 authorizing a development agreement with Microsoft

Van Meter City Council · official minutes recorded
Van Meter, Iowaagreement authorized
Sources and context

March 23 minutes are embedded in an April 13 packet. Authorization does not establish executed terms, all permits or operation.

construction update

Microsoft reports progress across Mount Pleasant construction phases

Microsoft said the first phase was nearing completion while later phases remained under construction or in earthworks.

Mount Pleasant, Wisconsinunder construction
Sources and context

Month-only update; this is not the site's opening date.