Walbridge participates in The Barn's construction and labor agreements.
Dated commitments & changes
construction update
Oracle reports a construction labor milestone at The Barn
Oracle reported that workers had reached a cumulative construction milestone at the Saline Township campus.
1,000,000 hoursCumulative union craft hourscompany reported labor inputThe Barn construction to the disclosed milestonestatedOracle / Josh Pitcock ↗
Saline Township, Michiganunder construction
Sources and context
The milestone occurred before publication; the exact achievement day is not disclosed. Craft hours are labor input, not a job count or proof of operating capacity.
OpenAI and its partners held a groundbreaking celebration for The Barn. Oracle reported that campus construction was already underway.
1 GWCampus capacityplanned data center capacityThe Barn campus, OpenAI announcementstatedOpenAI ↗
Saline Township, Michiganunder construction
Sources and context
The event date is the ceremony, not the start of all physical work. Related Digital develops the campus; Oracle supplies cloud infrastructure; OpenAI is the compute customer. Blackstone-affiliated funds and PIMCO-managed financing are distinct from the operator. Utility supply requirements may differ from the stated compute capacity.