Florida enacted SB 484 as Chapter 2026-65, approved May 7, 2026, with a general July 1 effective date and specified exceptions. It preserves local planning authority, requires minimum utility tariff and service protections for large-load customers, and restricts certain consumptive-water permits for large-scale data centers.
In the historical record
project approval
DeSoto County approves Roan Road rezoning and concept plan
The county records approval of a planned-unit-development rezoning and concept development plan for the DCIP project at NE Roan Road.
DeSoto County, Floridarezoning and concept plan approved
Sources and context
Approval concerns application RZNE0077-2025. The larger pending applications on the source page describe separate projects. Final construction permits and operating status have not been established. A roll-call tally was not verified.