Mississippi's Development Authority describes a data-center incentive providing sales-and-use-tax relief for qualifying equipment and software. Its April 22, 2026 Corderill announcement documents use of that program for a particular development. Announced assistance and projected jobs do not establish an operating facility or realized public benefits.
In the historical record
hearing notice
Mississippi posts notice of MZX permit evidentiary hearing
The notice schedules November 9 at 9 a.m. in Jackson, with continuation after the November 10 regular board meeting if needed.
Jackson hearing concerning Southaven permit 0680-00119hearing scheduled
Sources and context
Notice publication date; occurrence and outcome are not established by the notice. At November 10 retrieval, no ruling appeared in the inspected notice or 2026 minutes index.
SpaceX discloses MZX stormwater notices and preliminary exposure
The Q3 filing reports August notices alleging land disturbance before permit coverage, with roughly $6.1 million preliminary claimed exposure across three sites and resolution discussions underway.
Three MZX sites in Mississippienforcement resolution pending as disclosed
Sources and context
The date records disclosure of the notice; a final fine, settlement or payment has not been established. Stormwater compliance and turbine air permitting are separate regulatory processes.
MDEQ and MZX agree temporary-turbine retirement conditions
Order 7739 26 lists 69 temporary turbines, unit-specific retirement dates, biweekly reporting and testing; it bars new temporary units after July 15.
Stanton Road, Southaven, Mississippitemporary units subject to order
Sources and context
The state parties agreed operation had not violated Mississippi air-permit requirements; the later federal opinion rejected the mobile-source defense at dismissal. The December 31 deadline applies to SMT-130 units; other dates vary. Actual retirement compliance was not audited.
2875 Stanton Road, Southaven, Mississippiair construction permit issued
Sources and context
This is generation infrastructure supplying compute; it is not IT capacity or full campus approval. Permanent equipment is distinct from temporary turbines involved in the federal suit.